What should be included in work packages when accepting dependencies?

  1. All opinions from stakeholders

  2. Technical specifications from the IT department

  3. Development interfaces related to dependencies

  4. General statements of the project's goals

The correct answer is: Development interfaces related to dependencies

When accepting dependencies within work packages, it is essential to include development interfaces related to those dependencies. This ensures that any connections and interactions between different project components are clearly defined and understood. Development interfaces help to facilitate communication and integration among team members and teams, particularly in an Agile environment where collaboration is key. By detailing these interfaces, the work package can better accommodate dependencies, leading to smoother transitions and clearer expectations on how various elements will work together. In contrast, including all opinions from stakeholders may result in a lack of focus, as it could introduce subjective views that do not necessarily pertain to the technical requirements of the project. Technical specifications from the IT department, while important in some contexts, may not be directly related to the dependencies that need to be managed within the work package. Similarly, general statements of the project's goals do not provide the specific contextual details necessary for effectively managing dependencies. Therefore, emphasizing development interfaces ensures that project teams are aligned and can navigate interdependencies successfully.